Online
learning opportunities have significantly expanded the course offerings for
small school districts and my school wanted to capitalize on these possibilities.
At the time, our school district was experiencing instability in some key
leadership roles including the superintendent of schools and the high school
principal so I inherited the bulk of the online learning project.
The board of education, several teachers, and I decided to conduct a pilot program with well-defined constraints that included a limit of twenty students in their junior or senior year with a 3.0 or better GPA. The project team consisted of me, the library aide, the counselor, and the yet to be hired high school principal. The pilot program was officially acknowledged at a public board meeting but no formal project plan or documentation was developed. My responsibility was to identify content providers, develop a budget, establish a course catalog, and address technical issues. The counselor would screen students and assist them selecting an online course. The library aide was responsible for registering students in the online courses and supervising the students while taking the courses in the library. The future high school principal would provide mentoring and academic support. When I left for the summer, everything was in motion and ready for the start of school.
The board of education, several teachers, and I decided to conduct a pilot program with well-defined constraints that included a limit of twenty students in their junior or senior year with a 3.0 or better GPA. The project team consisted of me, the library aide, the counselor, and the yet to be hired high school principal. The pilot program was officially acknowledged at a public board meeting but no formal project plan or documentation was developed. My responsibility was to identify content providers, develop a budget, establish a course catalog, and address technical issues. The counselor would screen students and assist them selecting an online course. The library aide was responsible for registering students in the online courses and supervising the students while taking the courses in the library. The future high school principal would provide mentoring and academic support. When I left for the summer, everything was in motion and ready for the start of school.
Lynch
& Roecker (2007) define scope creep as uncontrolled deviations of the
projects requirements. Greer defines scope change “as any addition, reduction,
or modification to the deliverables or work process as outlined in your
original project plan” (2010, p. 35). Russell (2000), Stolovitch (Laureate
Education, 2010), and Portny et al (2008) all recommend managing and controlling
scope change with detailed scope of work documentation but concede sometimes
scope change is inevitable. When I returned to work several weeks prior to the
start of school, I discovered the interim superintendent capriciously removed
all of the student enrollment constraints in an effort to reduce class sizes.
Instead of twenty students, fifty-five from ninth through twelfth grade with no
GPA or other screening signed up for online courses. To further complicate
matters, the high school principal was not hired until October, the permanent
superintendent was hired the following March, and we were operating under severe
budget restrictions. This was a
situation we were completely unprepared for, causing many difficulties
throughout the school year.
Portny
et al (2008) advises risk analysis and contingency planning to prepare for
unexpected changes to project parameters. There was no contingency plan for
this debacle; only through long days and hard work were we able to get all of
the students enrolled in their online classes, some as late as three weeks
after the start of school. Because of the increased number of students, there were
not enough computers in the library for all class periods causing the library
to close when the aide was supervising in a computer lab. Over twenty-five
percent of the students failed their class due to a lack of screening and insufficient
academic support, over twice the classroom failure rate. In addition, I had to
explain to the new superintendent why the online learning budget was well over
two times the budgeted amount.
“What does not destroy me, makes me stronger”
~ Friedrich Nietzsche
While
the pilot program was a disaster by most accounts, I did learn enough to
advocate for sufficient resources for a full-scale online learning roll-out the
following year. In retrospect, I still see my options as limited. Insisting
adherence to the original constraints was not my decision and requesting
additional resources was flatly rejected. Better documentation of the process
and candid status reports at board meetings may have illuminated the problems
or may have further estranged me from the project.
References
Friedrich Nietzsche. (1888), Twilight of the Idols
Greer, M. (2010). The project
management minimalist: Just enough PM to rock your projects! (Laureate
custom ed.). Baltimore: Laureate Education, Inc.
Laureate Education, Inc.
(2010). [Video]. " Monitoring Projects."
Lynch, M. M., &
Roecker, J. (2007). Project managing e-learning: A handbook for successful
design, delivery, and management. London: Routledge.
Portny, S. E., Mantel, S.
J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E.
(2008). Project management: Planning, scheduling, and controlling
projects. Hoboken, NJ: John Wiley & Sons, Inc.
Russell, L. (2000). Project
management for trainers. Alexandria, VA: ASTD Press.



Dan,
ReplyDeleteWow! I empathize with you. I agree that your options were limited. All communication should be documented, especially changes in scope (Burdovich, 2012). How can you maintain control of scope and document communication when you are not there?
I find it very difficult to keep momentum of programs going due to the long summer break. I have also found that many things change over the summer even when personnel does not. It is difficult to establish a truly collaborative culture to keep lines of communication up with such breaks (Berry, 1993). A major change was the catalyst that pushed me to apply for the job that I have now. I had always wanted this job but had become complacent and let’s face it, applying and interviewing is not easy. I was the department chair for the self-contained special education department. I had worked diligently to schedule students into elective classes that matched their interests and I felt that they could be successful in. Over the summer, I checked my email to find an email stating schedules were not working out so the self-contained students were being taken out of all electives! This was going to involve IEP changes, angry parents, and disgruntled students.
Berry, J. E. (1993). Redefining Roles for Shared Decision Making: Organizational Leadership for School Systems. 2nd Annual Conference on Creating Quality School (pp. 1-14). Oklahoma City: ERIC .
Budrovich, V. (Performer) (2012). Practitioner Voices: You Can’t Win them All [Web]. Retrieved from https://class.waldenu.edu/webapps/portal/frameset.jsp?tab_tab_group_id=_2_1&url=%2Fwebapps%2Fblackboard%2Fexecute%2Flauncher%3Ftype%3DCourse%26id%3D_1373694_1%26url%3D
Dan,
ReplyDeleteThis seems to have been a tumultuous time for your team and unfortunately the students. I agreed with your reflection of Portny et al. regarding contingency planning for the project parameters, however as you noted a contingency plan could not have provided the necessary guidance for this situation. It’s quite obvious the interim superintendant was not aligned with the projects baseline initiated by your team. It would appear the interim superintendent would have considered seeking clarification of the project plan before readjusting or rebase-lining (Portny et al., 2008).
Portny et al. provides discussion with respect to assessing the magnitude of the consequences associated with risk where two pivotal points are made:
1. Consider how the impact of a risk effects the total project not just a small portion
2. Consider the impact of related risks when assessing their impact on the overall project
Your scenario provides critical insight into the importance for new members obtaining an understanding of the project scope upon joining a team; reviewing before acting and considering before suggesting. Unfortunately so many had to bear the pain of this change.
Robert J. Jackson
Reference
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.
Hi Dan,
ReplyDeleteWow! I can certainly empathize with you and what you encountered with the online learning project you were tasked with at your school. It sounds to me like it is quite common for projects to fall by the wayside during the summer breaks. In the case, it appears when you came back after 2 weeks, no one continued working on the project. The good news is that you learned from this project. I believe that is one of the most important things to realize when a project does not go well or as planned. As long as we can learn from the mistakes of the project to help us enhance our projects for the future, then this is certainly a good thing.
In Robert's comment above, he points out the importance of new members on a project team obtaining an understanding of the project scope upon joining the team. This is definitely a critical aspect of helping to ensure the project is successful, in case someone on the project team is not available for a period of time and others need to continue the work. It seems like when a project is going along smoothly, there are bumps in the road caused by unexpected changes. What sticks out to me from this week's reading that relates to your situation is about responding to scope creep and change control. As Portney, et al. (2008) mentions in section 11.5 about responding to scope creep and change control, "Avoiding scope creep is not possible. However, monitoring it, controlling it, and thereby reducing some of the pain is possible..." (p. 347). The specific guidelines outlined in the text are good to follow in order to effectively respond to scope creep and change control. Out of the guidelines listed, which one stands out to you the most?
All the best,
Jackie
References
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.
Dan,
ReplyDeleteThat is certainly a frustrating situation you had to deal with. I am glad you were able to persevere. Despite the less than positive turnout you were able to try a full-scale effort the next year. That is excellent. I am glad the district still saw the value after the prior year. I commend you for sticking with it.
It always amazes me when people take on a new job or role as your interim superintendent and do not consult the people who they are working with. Communication is so critical in general but especially important when taking on new responsibilities. How can you expect to make good decisions if you do not communicate and listen to the people who have been doing the work prior to your arrival?
Portny et al suggests that you have a contingency plan for new people coming onto the project but in your situation I can see that a plan would probably not been enough. You simply did the best you could to respond to the scope creep. It's funny the term sounds like the scope "creeps" but in your case it did way more than "creep".
Thank you for sharing.
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc